Your solar journey, step by step

Updated

Going solar happens in eight milestones. Most take place behind the scenes, but knowing where you are makes the wait easier — and helps you spot when something needs your attention.

Roadmap of the eight milestones from signing to In Service

How long does it take?

Scenario Typical time from signing to In Service
Smooth project About 3 months (12–14 weeks)
Most projects About 3½ to 4½ months (14–18 weeks)
Busy permit offices, utility backlogs, or extra work needed 5 months or more

The biggest variables are your city's permit office and your utility. Neither Solrite nor your installer controls their timelines, but we track every project and push when things stall.

The eight milestones

Milestone What happens Your part
1. Welcome You sign your agreement. Watch for your welcome and verification call.
2. Contract documents We verify your agreement, identity, and a recent utility bill. Answer the verification call; send any documents requested quickly.
3. System design Your system is designed and plans are prepared for the permit. Share access to your roof, attic, and electrical panel for the site survey.
4. Notice to Proceed Solrite reviews the design and approves installation. Nothing — we've got it.
5. Installation Your panels, battery, and equipment are installed. Be home (or arrange access) and clear the work areas.
6. Permission to Operate Your system is inspected (where your city requires it), then your utility approves turning it on. Sign the utility's interconnection agreement if they email it to you.
7. Solrite REP Partner enrollment (Texas) You enroll with a Solrite REP Partner for the grid electricity you still use. Complete the enrollment link Upgrid emails you.
8. In Service Your system is officially active and Solrite becomes your main contact. Download your monitoring app. Your first payment is due 30 days later.

Each milestone has its own article with more detail:

Where projects usually slow down

  • Permits — your city or county has a backlog.
  • Inspection — the inspector requests a correction and a re-inspection.
  • Utility approval (PTO) — your utility has a queue.
  • Missing paperwork — a document or signature is still needed from you or your installer.

Tip: The single best thing you can do to keep your project moving is to answer calls and emails from Solrite, your installer, Upgrid, and your utility promptly, and sign anything requested the same day.

Who to ask for an update

Until you're In Service, your installation partner manages your project schedule and has the latest information. If you've tried to reach them and can't, call us at (877) 705-7483, option 1 — we'll contact them on your behalf and ask them to reach out to you. See How to get a project status update.