After installation, your system needs your utility's Permission to Operate (PTO) — and, in most areas, a city or county inspection first.
City inspection (where required)
Not every city or county requires an inspection for solar. If yours doesn't, your project goes straight to the utility for Permission to Operate.
An inspector from your city or county checks that the installation meets code. Your installer schedules it, and someone may need to be home to give access.
If the inspector requests a correction, your installer fixes it and schedules a re-inspection.
Permission to Operate
Once the inspection passes (or right after installation, where no inspection is needed), your installer submits the paperwork to your utility. The utility reviews it and grants Permission to Operate — official approval to connect your system to the grid. Some utilities also replace or reprogram your meter.
Your utility may ask you to sign something
Utilities such as Oncor and CenterPoint in Texas often email homeowners an interconnection agreement to sign. This is legitimate and required. Please sign it promptly — your PTO can't be issued until you do.
Important: Don't turn on your system yourself before PTO. Operating before utility approval can violate your utility's rules.
How long does PTO take?
It depends on your utility — anywhere from a few days to several weeks. We track every project and escalate with the utility when PTO takes longer than expected.
What's next
- Texas: you'll enroll with your Solrite REP Partner. See Texas: enrolling with your Solrite REP Partner.
- Everyone: your system will be placed In Service. See You're In Service! What happens now.